5 Things That Go Wrong on Building Projects (and How to Design Them Out)

Writer: Roger Hines
Roger Hines
Oct 26
4 min read

Introduction


It's Halloween, so let's talk about what really haunts a building project.

It isn't ghosts. It's the problems nobody spotted before work started on site. They turn up halfway through the build, when changing anything is slow and expensive, and they land on the client's bill.


Before I designed houses, I built them. I've worked as a labourer, bricklayer, stonemason and foreman, and I ran a construction company. I've seen the same five problems come back on job after job. The good news is that every one of them can be designed out on paper, where a change costs a few minutes at the drawing board rather than a few thousand pounds on site.


Whether you're planning a new home, a replacement dwelling, a barn conversion or an extension, here's what to watch for.


1. Drawings that can't actually be built


The planning drawings look great. The render is beautiful. Then the builder asks how a corner, a roof or a big glazed opening actually goes together, and nobody has an answer.


This happens when a design is drawn to get through planning and the practical questions are left for later. By then the shape of the house is fixed by the planning approval. If the answer means changing the design, you may need to go back to the council.


How to design it out: work out how the house will be built while it is still being designed. Every key junction should be thought through before the scheme is submitted, not after. A drawing is only as good as the building it produces.


2. A budget nobody checked


The design grows a little at each meeting. An extra bay here, more glass there. Nobody tests the cost until the tenders come back, and the price has grown faster than the house.


What follows is "value engineering": stripping out the materials and details that made the design special, until the dream home becomes something else.


How to design it out: test the cost against the design from the first sketch. Choose a form and a construction method that suit your budget, and be honest early about where the money should go. It is far easier to design within a budget than to cut a design down to one.


3. "We'll sort it on site"


These are the five most expensive words in building. They usually mean a decision has been put off: how the stairs work, where the pipes run, what happens where two materials meet.


"We'll sort it on Site"

On site, those decisions get made in a hurry, by whoever is there, often while the trades stand waiting. The result is rarely what anyone would have chosen at the drawing board, and it is almost always more expensive.


How to design it out: make decisions on paper, where changes are cheap. Good construction drawings answer the questions before the builder has to ask them. That is also what lets builders price accurately, so you get fewer surprises in the quotes and fewer extras later.


4. Planning conditions left in a drawer


Planning permission usually comes with conditions: materials to approve, landscaping to agree, details to submit before work starts. Some must be discharged before anyone puts a spade in the ground.


It is surprisingly common for work to start, and then for someone to remember the conditions. The site stops until they are cleared, and the council can take weeks to respond.


How to design it out: plan for the conditions before they are issued. Expect what the council will ask for, have the information ready, and build the discharge into the programme so the start date is real.


5. The ground nobody looked at


Soft spots, old drains, a culvert, a tree root, a change in the ground halfway across the plot. If nobody looked before the design was fixed, the digger finds it. The client pays for it.


Ground problems are one of the most common causes of unexpected costs, especially on rural sites and replacement dwellings, where there may be old foundations, buried services or farm history under the surface.


How to design it out: investigate the site and the ground early, so foundations are designed rather than guessed. A modest spend on investigation at the start can save a far larger bill once work begins.


What they have in common


All five problems share one cause: decisions left until the build, when they should have been made in the design.


At Habitat, we call our approach detail first. The Building Regulations, buildability, the budget and the site shape the concept from the first sketch, rather than being bolted on after planning. Heat loss, sunlight, ventilation, structure and access all influence the form of the house before anyone sees a render.


It is also how we deliver what we call Stealth Performance: country homes that look traditional, in local stone and slate, but are designed to perform like a modern new build. They are warm, well ventilated, comfortable in summer and cheaper to run, without any compromise on how they look.



The house that gets planning permission should be the house that gets built. Designing it that way from the start is what keeps the nasty surprises away.


Five questions to ask your designer


Before you appoint anyone, or before you submit for planning, ask:


  1. How will this design meet Building Regulations?

  2. Has the design been checked against my budget, and when?

  3. Have the key junctions been worked out, or will they be decided on site?

  4. What planning conditions do you expect, and how will we deal with them?

  5. What do we know about the ground, and do we need a site investigation?


If the answer to any of them is "we'll deal with that later", that tells you something.


Planning a project in Lancashire or Yorkshire or further afield?


Habitat Architecture designs stone country homes, replacement dwellings, barn conversions and extensions across the Ribble Valley, Lancashire and North Yorkshire, from our studio in Clitheroe.